Roads and traffic
Change who attends a school and you change the roads they drive.
The school's traffic study was written in September 2024, before any of the three draft maps. Here is what it covered, what it did not, and what we could measure ourselves.
School trips
Some drives get shorter. Some get longer.
We modeled a representative car trip from 518 named subdivisions to each school's approach, today and under each draft. These are free-flow times. They leave out car lines, school-hour queues and bus stops.
Choto area to the new school · Scenarios 2 and 3
A.L. Lotts to Northshore · Scenario 3
Hardin Valley to the new school · Scenario 1
Our estimate Local road-network model on November 18 OpenStreetMap data. New-school trips end at Kingston Pike and Village Commons Boulevard, before the campus entrance. KCS published its own examples using Google Maps for a Tuesday at 7:15 a.m. Model and checks · KCS travel method, 30:45
The traffic study
What the 2024 study covers, and what it leaves open.
On the record
- Who and when
- Ardurra, New Farragut Elementary School Transportation Impact Analysis, September 6, 2024.
- What it models
- 1,400 students at full occupancy in 2031, about 3,178 vehicle trips a day, and 1.5% a year of background traffic growth.
- Where trips come from
- Estimated from the school zones of the time and School Board input. It assigns 60% of trips to the western, Watt Road side of Kingston Pike.
- Access
- 85% of trips use Village Commons Boulevard. 15%, buses and staff, use the rear entrance via Smith Road and Boring Road. It assumes no school traffic at Boring Road and Kingston Pike.
- Study area
- Five existing intersections near the campus.
Still open
- The draft maps. The study gives no results for any of the three November 2026 boundaries and no breakdown by neighborhood.
- Roads beyond the campus. Upstream routes such as Boyd Station Road, McFee Road and the Northshore and Concord roundabouts are outside the five intersections.
- Enforcement. In September 2026 the town engineer questioned how the Boring Road restriction would be enforced and expected parent traffic on that narrow route. The workshop took no formal action.
- Growth since 2024. McFee Road's daily count has more than doubled in ten years, and the latest Boyd Station Road count is up about 16% in a year.
- A newer version. We have not found a revision after September 2024. If one exists, it should be published with the final map.
Study area, report p. 9 · Trip distribution, report p. 19 · Access restriction, report p. 35 · Town engineer memo, packet pp. 3-4
One example
The Boyd Station underpass
Where Boyd Station Road meets Harvey Road and McFee Road, it passes under the Norfolk Southern railroad. The clearance is mapped at 10 feet 6 inches. KCS transportation staff said buses cannot fit and use the Concord roundabout instead.
We routed 120 sample homes in the Choto area to the parent entrance approach. 94 of them, 78%, passed through the underpass. That is a free-flow model of possible routes. It is not a traffic count, and it says nothing yet about queues.
It is a reason to count this spot at school hours under the boundaries actually proposed, and to show bus ride times alongside car times.
Our estimate Staff on bus routing, 35:38
Choto area to the new school, sample medians
| Route | Miles | Minutes |
|---|---|---|
| Car, through the underpassto the new school | 5.9 | ≈15 |
| By the Concord roundaboutthe route staff described for buses | 8.6 | ≈19 |
| To Northshore Elementary today | 8.3 | ≈18.5 |
Our estimate Free-flow car times for 50 sampled homes whose car route uses the underpass. Bus stops, dwell times and permitted bus routes are not modeled.
Road work
Construction planned on the school routes
Families comparing fall 2027 commutes should ask which roads will be open, and which will be work zones.
- Summer 2027
Overlaps opening - Virtue Road and Boyd Station, Phase 2. The town expects construction to start as the school opens. Wider lanes, curb and gutter and a shared-use path, reaching Boyd Station at Willow Cove Way. Town schedule · Funding, p. 78
- Under way in 2026
- Boyd Station at the Grove. Widening and a roundabout at the subdivision entrance. A partial closure was reported in April 2026. Current status unverified. Reporting
- By 2027
- Park entrance at McFee and Boyd Station. A second roundabout is proposed for the new 70-acre park. The grant requires recreational construction to begin by 2027. Town scope
- School approaches
- Boring, Smith and Village Commons. Road improvements approved in January 2025. The southern Boring Road connection to Kingston Pike was still under discussion in September 2026. Planning commission, item 4
- Possibly 2028
- South Northshore Drive, Choto to Concord. The county approved $565,745 for engineering in February 2026: about two miles with a center turn lane, sidewalk and a pedestrian tunnel between park areas. Scope · Schedule estimate
- 2040 horizon
- Harvey Road to McFee Road railroad overpass. In the regional plan at about $19.6 million. No construction phase in the current four-year program. The future of the existing underpass is not stated. Plan, project 24-608
Checked November 18, 2026.
Traffic counts
Daily traffic on nearby roads
Average vehicles per day, both directions. The dashed line marks 2024, when the school traffic study was written.
Knoxville Regional TPO and TDOT count stations. Some recent values are estimates between count years.
What remains open about school trips?
Routes for each draft
Parent and bus routes to their designated entrances under the boundaries actually proposed.
School-hour counts
Morning and dismissal volumes on the upstream roads, not only at the campus.
Before and after
Travel times for the same neighborhoods under current and proposed assignments, by car and by bus.
Fall 2027 roads
Which work zones and closures will be in place when the school opens.